Site Reports
Week ending Friday 18 April 2026
93
%
Dave's site is running at 93% optimised
High Wycombe is one of your best-performing sites this week. Strong attendance, proactive H&S management, shift compliance above target.
Workforce Optimisation Insights
Your site could be running at 97% with optimised shift scheduling and early absence alerting...
Today's Muster
113 workers · All signed in · Last: 07:48
✔ All Clear
All 113 workers signed on. Site fully manned as of 07:48.
113
/113
workers signed on today
Roll call — every dot is a person
This Week's Numbers
Attendance · H&S · Work Output
Strong
Attendance this week
H&S breakdown
Compliant
1 advisory
0 incidents
Attendance
91%
H&S
99%
Soon
Work Output
—
Vinnie Ellis · Supervisor
1 H&S advisory · 3 tasks this week · 1 in progress
1 advisory
Dust exposure — block cutting without RPE
Mon 14 Apr · 09:20
Groundworkers observed cutting concrete blocks on the eastern elevation without dust masks. Silica dust exposure risk. Toolbox talk issued immediately. All workers fitted with correct RPE before work resumed. No work stoppage.
Tasks this week
Concrete pour — Ground floor slab
Oversaw full pour sequence. Correct slump tested, vibration adequate, joints formed correctly. No issues reported.
Done
Toolbox talk — RPE and dust control
Issued to groundworkers following block-cutting observation. Silica dust hazards, RPE selection, wet-cutting procedures. 6 workers signed.
Done
Laydown area — trades materials
Supervised Tom Wright. Hardstanding complete. Zone marking and signage in progress.
Hardstanding100%
Zone marking & signage50%
75%